04.03.2024
Russian War Against Ukraine: Energy Dimension | DiXi Group Alert – weekly review 04.03.2024
February 26 – March 3
- As of March 4, 390 settlements remained without electricity due to hostilities and technological disruptions.
- The occupied Zaporizhzhia NPP remains without a backup power source, being completely dependent on a single 750 kV line. The occupants informed the IAEA on measures to “protect the facility”.
- Winter ended without a single blackout and use of outage schedules – so the PM Denys Shmyhal. He noted such steps as the creation of a stock of backup equipment, the restoration of 90% of the main grids, the addition of over 2 GW capacity, and the increase in gas production.
- As of late February 2024, over 1 million tons of coal had been accumulated in the warehouses of TPPs and CHPs, which is 236,000 tons more than planned – the Ministry of Energy. The capacity factor of NPPs reached 100%.
- The CEO of Naftogaz Oleksii Chernyshov reported that Ukraine passed the winter consuming only gas of domestic production, and announced plans to increase production by SOEs to 15 bcm.
- Due to a combination of factors, such as increased operation of RES and low consumption, a surplus emerged in the power system. As of March 2, 13 units of generating equipment at TPPs and CHPs were in reserve.
- Exports increased more than 2 times to 43.9 GWh. On the bilateral contracts market, the Base index for March amounted to 2,409.0 UAH/MWh (-22.5%), on the day-ahead market – decreased to 2,445.5 UAH/MWh (-16.6%).
- ENTSO-E has increased the permitted capacity of cross-border interconnectors for electricity exports from Ukraine and Moldova by 150 MW – to 550 MW. The first joint monthly capacity auction was held for the Ukraine/Moldova interconnection, thus completing the transition to European trading rules in all directions.
- The government improved the auction model of support for renewable electricity producers. In particular, contracts for difference are introduced instead of a fixed tariff, the conditions for participation are simplified for investors.
- Also, the Procedure for Issuing, Circulation and Cancellation of Guarantees of Origin of Electricity Produced from Renewable Sources and the Procedure for Determining the Environmental Value of Electricity were approved.
- On March 3, the NEURC members elected Valerii Tarasyuk as Chair by secret ballot.
- The EU Regulation establishing the Ukraine Facility, a four-year assistance program totaling 50 billion EUR, entered into force. In March, the government will approve the Ukraine Plan envisaging structural reforms – so the First Vice PM Yulia Svyrydenko.