The Ministry of Energy has recently resumed work on the implementation of the National Emissions Reduction Plan for Large Combustion Plants (the NERP), but soon proposed to postpone its implementation.

The history of drafting the relevant legislation began in 2011, when Ukraine joined the Energy Community. One of the commitments was to implement a directive regulating emissions for the large combustion plants, including the thermal power plants and combined heat and power plants. Initially, by January 1, 2018, Ukraine had to implement Directive 2001/80/EC, but there was almost no progress. Subsequently, the EU adopted Directive 2010/75/EU with more stringent requirements. The clause on the new directive was included into the Association Agreement between Ukraine and the EU with implementation until September 1, 2019 (2 years from the date the Association Agreement entered into force).

Thus, the government had to implement both regulations at different stages, with different deadlines. De jure, Ukraine implemented the first directive (2001/80/EC), but in fact this did not happen since the process would require considerable costs from the industry, as well as the state support for the business. Realizing that it would have no time to comply with the requirements by January 1, 2018, the government, as a result of negotiations with the European party, agreed to omit compliance with these regulations immediately moving to a later directive with higher standards (2010/75/EU). When in 2013 the Ministerial Council of the Energy Community allowed developing the national emissions reduction plans instead of introducing the limitation of emissions for each plant, Ukraine used this option. Due to the fact that almost all the large thermal power plants and electric power plants were not ready for such an expensive upgrading, it seemed impossible to meet the requirements in the same timeframe as the EU countries.

Although in 2017 the Cabinet of Ministers of Ukraine adopted the NERP, almost nothing has been done to make it work. On the one hand, the final plan goals are a rather high standard. However, according to the document, a lot of time is allocated to achieve them: in the period of 2018 through 2028, SO2 emissions should be 20 times less, dust – 40 times less and NOx emissions – 3.5 times less to the end of 2033. However, having prescribed the requirements to be met by the plants, the legislation did not provide for the sources of funding for their upgrading, which paused the plan implementation. The amount of funds required is estimated at EUR 4.13 billion.

Failure of the large combustion plants to meet the established requirements means the need to stop their activities. Of course, the option to close all such facilities is not viable and is not being considered by the government. For the electricity generation sector, this will create the risks of disrupting the energy system stability, especially in the context of integration into the ENTSO-E. The thermal power plants and combined heat and power plants account for a significant share of the total generation – about a third of the total volume in September 2020. Unlike the nuclear power plants or generation from the renewable sources, the thermal power plants are important for the energy system balancing. It will not be possible to replace them quickly since no tenders for construction of the new highly maneuverable capacities and energy storage systems have been announced yet. Therefore, it is necessary to ensure the timely upgrading or decommissioning of TPPs and CHPPs, but such measures shall be scheduled in advance.

However, the government decided to go the easy way and postpone the implementation of the European standards again. In October 2015, the Ministerial Council of the Energy Community made a decision to postpone the implementation of Directive 2010/75/EU by Ukraine. In July 2019, the Cabinet of Ministers of Ukraine approved amendments to the NERP in order to, among other things, postpone the implementation of the environmental measures for TPPs. According to the industry representatives, keeping the NERP in the then-effective version would lead to the forced shutdown of 22 power units in 2020-2025, electricity shortages and threats to the energy security.

The government is using similar arguments now. In September 2020, the Ministry of Energy asked the Energy Community to postpone the plan implementation for five years. According to Maksym Nemchynov, the Deputy Minister, the agency is working to establish the adequate deadlines for the NERP implementation, to update the facilities list (taking upgrading or reconstruction into account, as well as changes in the energy balance), to develop the financing mechanisms and negotiate with the international partners and market participants.

However, given the previous dynamics, it is reasonable to suppose that the Ministry of Energy will pay more attention to postponement than to search for the re-equipment resources. Mr. Janez Kopac, Director Energy Community Secretariat, was skeptical of the government’s intentions, promising to submit Ukraine’s proposal to the European Commission, but noted that it would be difficult to prove its expediency. After all, the EU aims to strengthen the high environmental standards vector in the framework of the European Green Deal (the EGD). Moreover, the EU expects Ukraine to become an important partner in the implementation of the EGD and will continue to harmonize its legislation with the updated European one, not to mention the commitments undertaken in the previous periods.

It should be noted that the implementation of the requirements for the combustion plants is a complex and lengthy process requiring, at least, 10-15 years. If the implementation of the NERP is postponed for another five years, it means that coal generation will fully meet the environmental requirements no earlier than 2040. In addition, the reduction of the industrial pollution affects not only the international obligations and European integration, but also health of the Ukrainians. Raising environmental standards should be among the first place interests of Ukraine itself, and not of its foreign partners.

Therefore, now it is extremely important for the government to take decisive steps to find the sources of funding for upgrading and re-equipping the relevant facilities in accordance with the NERP. Financial decisions may include adding a part of the re-equipment costs to the electricity tariff subject to the PSO abolition, budget support, loans from the international financial institutions and funds of the plant owners. Possibly that the EU would make advances to Ukraine and extend the terms for complying its commitments. But it is not enough to demonstrate intentions to act, it is necessary to start acting. If, however, after a while from starting the implementation of the NERP, for example, in five years, it becomes clear that the industry is not fulfilling it on time, then we can talk about revising the deadlines. Postponing the plan implementation is the most inert way that will not eliminate the existing problems, but will only postpone the decision-making.

Comments

img

Daryna Kulaha

Junior analyst DiXi Group

The government’s intentions to postpone EU environmental requirements are unlikely to receive the foreign partners’ support

The Ministry of Energy has recently resumed work on the implementation of the National Emissions Reduction Plan for Large Combustion Plants (the NERP), but soon proposed to postpone its implementation.

img

Olha Polunina

Sustainable Development Manager

Approved reporting forms are a step towards greater transparency in production

The government has finally approved reporting forms for extractive companies developed, inter alia, with the participation of DiXi Group experts.

img

Daryna Kulaha

Junior analyst DiXi Group

No effective solutions on debts to “green” generation have been proposed yet

The government has actually held the Regulator and the transmission system operator fully responsible for resolving the situation

img

Olena Pavlenko

DiXi Group President

Halting Nord Stream 2 must become a part of the EU’s “single voice”

The tragic poisoning of Russian opposition activist Alexei Navalny changed the stance of the German political elite. The insistence on purely German interests has weakened, and today, Germany is more open to forming a common European stance as far as interaction and communication with Russia are concerned.

img

Roman Nitsovych

DiXi Group Research Director

What the new law on “green” energy “fell short” of

It seemed that the long-running “serial” of political discussions between the government and investors in renewable energy has ended. But in fact, the new law may not solve the problem after all, as there are at least five reasons for that.

img

Roman Nitsovych, Research Director, DiXi Group

Darina Kulaga, expert consultant

Only an increase in the transmission tariff will not solve the crisis in the electricity market

The tariff increase will not affect electricity prices for household and small non-household consumers, but will be felt for industry and other consumer groups. The main purpose of this step is to ensure stable revenues for timely payments to producers of electricity from renewable sources.

img

Bohdan Serebrennikov

Manager on consultancy and analytical services

The current electricity market is not yet the model we are striving for

The current market, with many regulatory price caps, unbalanced RES support policy, non-market prices for the population and an existing mechanism of assignment of special obligations (ASO), is not like the model being built in the EU.

On the way to the gas market. What changes the regulator’s decision and what needs to be done?

National Energy and Utilities Regulatory Commission (NEURC) adopted the decision simplifying the procedure for changing the gas supplier for household consumers

img

Bohdan Serebrennikov

Manager on consultancy and analytical services

04 ЧЕРВНЯ 2020

Ukrainian model of Public Service Obligations significantly distorts the electricity market

Since electricity prices are the same for the entire population throughout Ukraine, the current PSO model protects not only economically vulnerable but also wealthy consumers, which seems economically unjustified. Moreover, prices for households have not changed since March 1, 2017.

img

Bohdan Serebrennikov

Manager on consultancy and analytical services

01 ЧЕРВНЯ 2020

Lack of prerequisites for unbundling of electricity bills

However, current tariff, even its upper rate, does not reflect real costs incurred for the production, procurement and supply of electricity to households, since the country uses hidden cross-subsidization of the population through the mechanism of Public Service Obligations (PSO).

img

Roman Nitsovych, DiXi Group Research Director

Anastasiia Synytsia, Analytical Department Trainee

26 ТРАВНЯ 2020

European Green Deal and Ukrainian energy: quo vadis?

During the operation of the united Ministry of Energy, it was not possible to synchronize the climate and energy directions. For more than 6 months the government and key participants of the renewable energy market have been unable to agree on a solution to the industry’s problems.

img

Roman Nitsovych

DiXi Group Research Director

18 MAY 2020

Decision concerning Nord Stream 2: the final victory still needs to be fought for

The decision of German regulatory authority, BNetzA, concerning the legal framework in which Nord Stream 2 can operate represents an interim victory of Ukraine.

img

Andrii Ursta

trainee at DiXi Group Analytics Section

15 APRIL 2020

How steady is the trend of declining fuel prices?

Pricing in Ukraine’s retail market for petroleum products draws close attention from both consumers and public authorities. Telling facts in this sense are meetings of the President with representatives of filling station chains or the AMCU’s in-depth analysis of actions of petroleum products market participants, which the agency started in January of this year.

img

Roman Nitsovych

Research Director

13 КВІТНЯ 2020

Oil producers unite before the danger of “execution”

If implemented, the preliminary agreement of OPEC+ countries will allow to somewhat stabilize oil prices in the nearest few months, but it remains to be seen whether it will restore the balance of demand and supply in the market.

img

Olha Polunina

Manager for Sustainable Development

10 APRIL 2020

EIA: a problem or an indispensable element of sustainable development?

Back in 2016, the Verkhovna Rada of Ukraine passed the Environmental Impact Assessment Law. From the very beginning, the implementation of this legislative act has bumped into obstacles: the law was vetoed after an appeal by the Association of Pig Breeders of Ukraine, whose representatives believed that it would bring their industry to a standstill.

img

Bohdan Serebrennikov

Manager on consultancy and analytical services

09 APRIL 2020

Coronavirus and systemic imbalances of the electricity market

Today’s crisis in the electricity market is not just a concurrence of circumstances caused by a seasonal factor and by quarantine restrictions. These factors vividly illustrated, and stretched almost to its limits, the vulnerability of the system in which Ukraine’s electricity market functions in its present form.

img

Roman Nitsovych

Research Director

08 APRIL 2020

A “perfect storm” in the oil market

Today’s situation in the global oil market is a “perfect storm” for oil producing countries, but for countries importing petroleum products, it presents an opportunity to stock oil on the cheap.

Our platforms

img

Website of the coalition which unites experts from leading think tanks and NGOs in the field of energy and environment 

img

National website of Extractive Industries Transparensy Initiative in Ukraine 

img

Information and analitical website “Ukrainian Energy UA-Energy.org” is unique   platform to inform

img

Independent platform for public dialogue on the issues of unconventional gas exploration and production

Our platforms

img

Website of the coalition which unites experts from leading think tanks and NGOs in the field of energy and environment 

img

National website of Extractive Industries Transparensy Initiative in Ukraine 

img

Information and analitical website “Ukrainian Energy UA-Energy.org” is unique   platform to inform

img

Independent platform for public dialogue on the issues of unconventional gas exploration and production